JNV / Khurda / Phase - "A"
Cost As Per revised A / A & E/S 860.31 Lacs
Cost As Per Final Bill (Tentative) Excluding Contingency & C/A Charges 852.77 Lacs
Date of Commencement 18/01/2008
Date of Handing Over 01/10/2009
Sl. No.
Name of building
 
Plinth Area
Actual cost in Lacs
 
1
School Building
 
1913 Sqm
226.2
 
2
Boys Dorm with WR - 4 Nos.
 
1603 Sqm
189.55
 
3
Girls Dorm with WR - 2 Nos.
 
802 Sqm
94.77
 
4
Kitchen / Dining
 
757 Sqm
89.51
 
5
Staff Qr. T - V (1 No.)
8×60 Sqm
106 Sqm
12.53
 
6
Staff Qr. T - III (8 No.)
8×50 Sqm
480 Sqm
56.75
 
7
Staff Qr. T - II (4 No.)
8×40 Sqm
200 Sqm
23.64
 
8
Staff Qr. T - I (4 No.)
 
160 Sqm
18.92
 
9
Electric Sub Station
 
40 Sqm
4.73
 
10
Pump House
 
7.0 Sqm (Appx.
0.95
 
11
OHT1.00 lasc Liter
   
20
 
12
UGT1.00 lasc Liter
   
5.35
 
13
D.G.SET 25 KVA
   
4.00
 
 
Total Including External & Internal Electrification Complete.
   
746.9
 
14
CC Roads
       
 
3.50 M Wide
 
330.0 Mts
   
 
3.00 M Wide
 
277.0 Mts
   
 
7.00 M Wide (K / D)
 
08.0 Mts
   
 
5.40 M Wide (Front of SB)
 
23.60 Mts
   
 
6.60 M Wide (Front of SB)
 
06.65 Mts
   
 
4.30 M Wide (Front of SB)
 
10.3 Mts
   
15
Foot Path
       
 
1.50 M Wide
 
391.0 Mts
   
 
1.20 M Wide
 
118.70 Mts
   
 
2.30 M Wide T - I
 
3.70 Mts
   
 
2.45 M Wide T - II
 
2.45 Mts
   
 
Total cost of Development Work including Roads, Foot paths, drainage, Sewerage, Septic tank, Soak Pits sentry Room & Boundary wall
   
105.87
 
 
Total Cost of Project (Tentative as the final Bill is still under Checking)
   
852.77